Africa Establishment Time Frame

Project planning and Management

Phase – I Second Quarter 2022

Sewing Factory Research & Development 
Developing Sewing Factory Project according to the present customer’s expectation and based on the planned/acquired investment. (Finished)
Hiring team heads to handle the subsections of projects from the whole project, kind of Civil, Electrical, Mechanical, designing of civil heads etc.,
Contract establishing/finalizing like Civil, Steel Structure, Consultant, Land leasing, Registration etc.,
Finding and deciding the appropriate Sewing Machines, CAD, CAM as per the Customer’s and Style requirement. (Finished)
Finding and deciding other equipment and utilities for the total project
Start Communication for entire project materials and machine companies etc.,
Sourcing and purchasing the decided sewing machines and other equipment’s to set-up sewing factory based on the basic plan.
If it is necessary, finding and Sourcing the Used machines from various parts of the world.
Negotiate the Price, Delivery, Erection and maintenance work with machine manufacturers.
Estimating the required Furniture, Wiring and Power house and vehicles for Sewing factory as well as total project.
Project materials Sourcing and Purchasing from various part of the world, especially from India, Taiwan, Japan, Germany, Italy, USA., UAE and China.
Arranging and meeting with the manufacturers at their factory.
Space and Line planning and installing machines
Bank Loan Management with finance team
Training and Development with production team
Discussions with the teams about Technical points and execution

Phase – II Third Quarter 2022

Knitting and Fabric Processing Unit
Research & Development 
Developing Knitting, Cone Winding, Collar Knitting, Dyeing, Washing, Drying, Wet process and Compacting Project according to the owned Sewing capacity, even to execute CMP orders as a job work and as per the Customer’s expectation.
Waste water treatment; (RO Plant) estimating (including the Printing Unit for Phase – III)
Hiring team heads to handle the subsections of projects from the whole project, kind of Civil, Electrical, Mechanical, designing of civil heads etc.,
Contract finalizing; like Civil, Steel Structure, Consultant, Land leasing etc., if any pending or unfinished works
Finding and Deciding the Machine’s as per the Style requirement and Customers requirement. Fulfilling and Adding job work needs to find additional income to the total project in future.
Finding and deciding other equipment and utilities for the main project
Start negotiations for entire project materials and machines with manufacturers etc.,
Sourcing the required Capacity fulfilling machines and other equipment’s to set-up Knitting and Processing factory.
If it is necessary, then Finding and Sourcing the Used machines from various parts of the world.
Negotiate the Price, Delivery, Erection and maintenance work with machine manufacturers.
Estimating the required Furniture, Wiring and Power house and vehicle for the Knitting and Processing Unit.
Project materials Sourcing and Purchasing from various part of the world, especially from India, Taiwan, Japan, Germany, Italy, USA, UAE and China.
Space and Place planning and installing machines
Loan Management
Training and Development
Discussions with the teams about Technical points and execution

Phase – III Fourth Quarter 2022

Printing, Curing and Embroidery to add value to the Garments
Research & Development 
Developing Printing and Embroidery Project according to the handling styles and Customer’s expectation.
Hiring team heads to handle the subsections of projects from the whole project, kind of Civil, Electrical, Mechanical, designing of civil heads etc.,
Contract finalizing like Civil, Steel Structure, Consultant, Land leasing etc.,
Finding and Decide the Machines as per the Customer’s and Style requirement. Fulfilling and adding job work needs to find additional income to the total project in future.
Finding and deciding other equipment and utilities for the main project
Start negotiations for entire project materials and machines with manufacturers etc.,
Sourcing and purchasing the required Capacity fulfilling machines and other equipment’s to set-up Printing, Curing, Compacting and Embroidering
Negotiate the Price, Delivery, Erection and maintenance work with machine manufacturers.
Estimate the required Furniture, Wiring, Power hub and vehicle for Printing and Embroidery plant.
Machine and materials are sourcing from various part of the world, especially from India, Taiwan, Japan, Germany, Italy, USA, UAE and China.
Space and Place planning and installing machines
Loan Management
Training and Development
Discussions with the teams about Technical points and execution

Internal Administration about the Project

Collecting reports from Contractors and Sub-Contractors and submitting them to the investors time to time through Website, Twitter, Telegram, WhatsApp, Direct mail and other social media
Providing and collecting Technical support from each team and forwarding to Investors for their information
Ensuring effective and efficient Co-ordination between teams
Arranging meetings with teams and within the team
Building relationships with Government Authorities Like Ministry of Labor etc.,
Building relationship with Bank and loan authorities
Through effective communication, developing very good relationships with the community and maintaining a good eco system
Documenting video recording of every step and posting it in social Medias
Monthly online meeting with investors to explain the ongoing things

Estimated Time Frame for each phase

Phase – I
Sewing Factory– Steps involved and Estimated Time frame for each Steps: –

Collecting the Requirement advice
Finding the Required Machines against the capacity or Investment
Estimating the area requirement
Estimating the Constructed area requirement
Land leas etc.,
Contractor finding and finalizing for construction
Collecting advice from Contractor about required construction materials
Acquiring Construction materials from various parts of the world
Estimate the construction completion date
Finding the required number of each machine (ALREADY COMPLETED)
Finding Manufacturer of each different machines
Establishing negotiation and discussion with each manufacturer
Price negotiation, Visit to the machine manufacturer
Confirmation and payment for each item
Logistics and Importing
Preparing the Local purchase items
Preparing and purchasing electrical equipment’s
Machine erection, furnishing, wiring compiling
Vehicle purchase
Staff hiring
Labors hiring
Training to staffs and labors
Arrange buyer visit
Do sample orders
Do Local orders
Prepare sampling
Arrange and Attend buyer visit
Attending Trade Fair
Collect orders from customer
Unidentified works and delay

Number 1 to 9 is a set of work, the same way Number 10 to 17, 18&19, 20 to 22 and 23 to 28 are sets of works. Can complete these works within EIGHT MONTHS. That means the factory may start its work within eight months.

Unidentified delays may happen in Bank loan, construction, importing the construction material and fulfilling the legal formalities area.
Fund is very important to complete the project on time.
Above defined set of works have deep connection in each other, the work, inside of the set; also have interconnection. One set can’t be started without completion of the previous set. Each set dependent on others. This may also cause delays.

Estimated Time frame: – From April 2022 to June 2023

Month – 1: – Basic Plan; Government formalities like land leas; Based on the basic plan identifying the required machines and other utilities; Arrange Driver and Vehicles; Complete the basic project plan for bank work. Apply for a loan for building and machine. Hire If Staffs required for Bank follow-up, Govt Office follow-up, Documents and Shipping follow-ups.

Month – 1 & 2: – Government formalities; Based on the basic plan identifying the required machines and required building space; Bank formalities; Negotiating Contractors, Assigning Contactors; Hire security. Start Office building construction work. Start negotiation with machine manufacturers, collect quotation. Compare the durability of the machine. Choose the planned to buy machines and utilities.

Month – 2 & 3: – Based on the basic plan identifying the required machines; Start negotiation with machine manufacturers, collect quotation. Arrange visits to the machine manufacturers. Co-ordinating the contractors to find and estimate the Factory building space; Office construction; Factory construction materials estimate; Wiring requirements estimation; Finding wiring contractors; Sourcing the material manufacturers for factory; Price and other terms negotiation. Order placing.

Month – 3 & 4: -Continue negotiation with machine manufacturers, collect quotation. Machine Sourcing from various parts of the world, meeting with Machine manufacturers; Price and other terms negotiation. Co-ordinating the contractors; Office construction; Ensure the Quality of the Factory construction materials through technical team; estimate additional needs; Establish Wiring Contract; Collect wiring needs; Sourcing the material manufacturers for factory; Price and other terms negotiation. Order placing. Order follow-up; logistic; import and import formalities follow-up. Deploying all necessary materials; follow-up construction.

Month – 4 & 5: – Continue negotiation with machine manufacturers, finalize quotation. Machine Sourcing from various parts of the world, meeting with Machine manufacturers; Price and other terms negotiation. Co-ordinating the contractors; Office construction; Ensure the Quality of the Factory construction materials through technical team; estimate additional needs; Establish Wiring Contract; Collect wiring needs; Sourcing the material manufacturers for factory; Price and other terms negotiation. Order placing. Order follow-up; logistic; import and import formalities follow-up. Deploying all necessary materials; Construction follow-up; Finalizing the needed machinery; Finding the used machines; Order placement; Shipping, import follow-up. Finding a place to store the imported machines and other utilities

Month – 5 & 6: – Continue negotiation with machine manufacturers, collect quotation. Machine Sourcing from various parts of the world, meeting with Machine manufacturers; Price and other terms negotiation. Co-ordinating the contractors; Office construction; estimate additional needs; Establish Wiring Contract; Collect wiring needs; Sourcing the material manufacturers for factory; Price and other terms negotiation. Order placing. Order follow-up; logistic; import and import formalities follow-up. Deploying all necessary materials; Construction follow-up; Finalizing the needed machinery; Finding the used machines; Order placement; Shipping, import follow-up. Finding place to store the imported machines and other utilities; Construction follow-up; Store things and develop tracking. Wiring and Machines erection; interview started for each position as well as Labor and securities.

Month – 6 & 7: – complete the office construction. Finalize the Factory construction. Develop machine lay plan to use raw materials with easy movements. Install the machines, arrange mechanics. Fill the vacancies; Hire Consultants; Buy Fabric and Trims; Start training for Staffs and Labors. Arrange Telephone and Internet connections.

Month 7 & 8: – Deploy the machines as per lay plan., Install the machinery connecting roads. Install the machinery. Install the power house. Install electrical wiring works. Fill the vacancies, Continue the training; Do Sampling orders; Do Local orders; Arrange Buyer meetings; Visit Buyer Office; Collect Trail orders; Prepare buyer sampling; attend the Trade Fairs.

Month – 8 to 10: – Find errors and rectify the errors. Do Local orders on CMP basis. Visit Buyer Office, meet Customers, Develop Samples for each Customers, Develop Website, develop marketing, Start export orders in CMP Basis. Find additional requirement according to the Customer needs.
Basic Plan for Knitting and processing Unit; Government formalities; Based on the Sewing Capacity, identifying the required machines and other utilities; Apply loan for building and machine.

Phase – II
Knitting & Fabric Processing – Steps Involved – Estimated Duration for each step
Steps Involved: –

Collecting the Requirement advice
Find the Capacity need as per the Sewing Capacity
Finding the Required Machines
Estimating the area requirement, Allocate the Factory Space.
Estimating the Shed area
Land leas, Bank Loan etc.,
Contractor finding and finalizing for construction
Collecting advice from Contractor about required construction materials
Acquiring Construction materials from various parts of the world
Estimate the construction completion date
Finding the required number of each machine
Finding Manufacturer for each different machine
Establishing negotiation and discussion with each manufacturer
Price negotiation, Visit to the machine manufacturer
Confirmation and payment for each item
Logistics and Importing
Preparing the Local purchase items
Preparing and purchasing electrical equipment’s

Inviting mechanics from each machinery manufacturer
Machine erection, furnishing, wiring compiling
Vehicle purchase
Staff hiring
Labors hiring
Training for staff and laborers
Arrange buyer visit
Do sample orders
Do Local orders
Prepare sampling
Arrange and Attend buyer visit
Attending Trade Fair
Collect orders from customer
Unidentified works and delay

Estimated Duration for each step: –

It is a continuation from the previous project, however according to the fund it is possible to start earlier or on time of previous project. So, Phase II’s Starting month is denoted here as Month 4.

Month – 4 & 5: – Basic Plan; Government formalities; Based on the Sewing Capacity identifying the required machines and other utilities; Apply loan for building and machine.

Month – 5 & 6: – Government formalities; Follow-up loan for building and machine. Negotiating Contractors, Assigning Contactors; Start negotiation with machine manufacturers, collect quotation. Compare the durability of the machine. Choose the planned to buy machines and utilities.

Month – 6 & 7: – Assigning Contactors; Co-ordinating the contractors to find and estimate the Factory building space; Factory construction materials estimate; Wiring requirements estimation; Sourcing the material manufacturers for factory; Price and other terms negotiation. Order placing. Start negotiation with machine manufacturers, collect quotation. Arrange visits to the machine manufacturers. Choose the planned to buy machines and utilities.

Month – 7 & 8: – Logistic follow-up for factory construction materials, Arrange local purchase items. Continue negotiation with machine manufacturers, collect quotation. Machine Sourcing from various parts of the world, meeting with Machine manufacturers; Price and other terms negotiation. Find Used machines around the world. Choose the planned to buy machines and utilities. Order placing. Order follow-up; logistic; import and import formalities follow-up. Deploying all necessary materials;

Month – 8 & 9: – Continue negotiation with machine manufacturers, finalize quotation. Machine Sourcing from various parts of the world, meeting with Machine manufacturers; Price and other terms negotiation. Co-ordinating the contractors; Office construction; Ensure the Quality of the Factory construction materials through technical team; estimate additional needs; Establish Wiring Contract; Collect wiring needs; Sourcing the material manufacturers for factory; Price and other terms negotiation. Order placing. Order follow-up; logistic; import and import formalities follow-up. Deploying all necessary materials; Construction follow-up; Finalizing the needed machinery; Finding the used machines; Order placement; Shipping, import follow-up. Finding a place to store the imported machines and other utilities

Month – 9 & 10: – Continue negotiation with machine manufacturers, collect quotation. Machine Sourcing from various parts of the world, meeting with Machine manufacturers; Price and other terms negotiation. Co-ordinating the contractors; estimating additional needs; Establish Wiring Contract; Collect wiring needs; Sourcing the material manufacturers for factory; Price and other terms negotiation. Order placing. Order follow-up; logistic; import and import formalities follow-up. Deploying all necessary materials; Construction follow-up; Finalizing the needed machinery; Finding the used machines; Order placement; Shipping, import follow-up. Finding place to store the imported machines and other utilities; Construction follow-up; Store things and develop tracking. Wiring and Machines erection; interview started for each position as well as laborers and securities.

Month – 10 & 11: – Finalize the Factory construction. Finalize wiring. Develop machine lay plan to use raw materials with easy movements. Install the machines, Arrange mechanics. Fill the vacancies; Buy Yarn, Fabric and Trims; Start training for Staffs and Labors. Arrange Telephone intercom to factory shed. Import dye stuffs and printing stuffs. Arrange stores to keep chemicals.

Month – 11 & 12: – Deploy the machines as per lay plan. Install the machinery. Install the power house. Complete electrical wiring works. Fill the vacancies, Continue the training; Do Sampling orders; Do Local orders; Arrange Buyer meetings; Visit Buyer Office; Collect Trail orders; Prepare buyer sampling; attend the Trade Fairs.

Month – 13 to 14: – Find errors and rectify the errors. Do Local order in full package basis. Buy trims and accessories as per the order’s needs. Visit Buyer Office, meet Customers, Develop Samples for each Customers, Update Website, develop Marketing, Start Export Orders as full package basis. Find additional requirement according to the Customer needs.

Phase – III
Printing and Embroidery to add value to the Garments
Steps Involved: –

Collecting the Requirement advice
Finding the Required Machines as per the in-hand customer’s need
Estimating the area requirement
Estimating the Constructed area requirement
Allocate the space from the shed
Finding the required number of each machine
Finding Manufacturer of each different machines
Establishing negotiation and discussion with each manufacturer
Price negotiation, Visit to the machine manufacturer
Confirmation and payment for each item
Logistics and Importing
Preparing the Local purchase items
Preparing and purchasing electrical equipment’s
Machine erection, furnishing, wiring compiling
Staff hiring
Labors hiring
Training for staff and laborers
Arrange buyer visit
Do sample orders
Do Local orders
Prepare sampling
Arrange and Attend buyer visit
Attending Trade Fair
Collect orders from customer

Estimated Duration for each step: –

Month – 4 & 5: – Find the required machines, Find the machine manufacturer, Start negotiation,

Months 5 & 6: – Place order and do follow-up. Buy raw materials to run Printing and Embroidery

Months – 7 & 8: – Logistic work to import machinery.

Months – 8 & 9: – Deploy the machine at allocated place, Start erection. Do Samples. Hire staff and laborers. Start training.

Months – 9 & 10: – Update website; Collect orders from local manufacturers and importers. Start and Co-ordinate to work with Sewing factory.

Months – 11 & 12: – Finalize the Custom Jersey order designing website with all tools and start to accept orders from USA, Canada, and Europe customers. Customer can design their Styles, Size, Color, Print, and Embroidery from the collective designs and fabrics. Tokens will work to buy the custom jerseys on the website with other currencies.
Customers can order Sports Garments, Team Garments, and School Uniforms through the website. Customer’s orders will be packed and sent to country head delivery address all together as one shipment, from there each pack will courier to the individuals. So, transportation will not affect the selling price. So, within a month individual customers will get their custom designed garments on their door’s steps at a competitive and cheaper price.